John D. Sulsberger

Memorial Stadium
Home (of the Blue Devils)
How You Can Help!
The Renovations
Photo Galleries / 2009
Photo Galleries / 2008
April 30, 2008
May 2, 2008
May 6, 2008
May 9, 2008
May 12, 2008
May 13, 2008
May 14, 2008
May 19, 2008
May 23, 2008
May 28, 2008
May 29, 2008
June 2, 2008
June 4, 2008
June 10, 2008
June 11, 2008
June 13, 2008
June 18, 2008
June 19, 2008
June 23, 2008
June 26, 2008
July 2, 2008
July 7, 2008
July 8, 2008
July 9, 2008 (Early)
July 9, 2008 (Late)
July 11, 2008
July 13, 2008
July 15, 2008
July 16, 2008
July 17, 2008
July 19, 2008
July 21, 2008 (Early)
July 21, 2008 (Late)
July 23, 2008
Aug. 4, 2008
Aug. 13, 2008
Aug. 15, 2008
Aug. 21, 2008
Who was John Sulsberger?
Building the Stadium-1964
Stadium Facts
The Latest News
Contact Us
Site Map
July 21, 2008 - Early
 Grinding it out!
 

 
The asphalt that was the base of the track began to be milled in high spots today. Eventually, the surface will be pre-leveled to also fill some low spots, then given a smooth top layer before the rubberized track surface is applied.
 
 
The excess asphalt was quickly milled off and poured into a waiting dump truck.
 

 
The west end of the field was still being done, as stone was brought in to help build up the area and prepare it for paving. The high jump will be contested in this area of the stadium.
 

 
Meanwhile, the last of the four new light poles were wired for power today. Here the electricians prepare to pull the wire up to the transformer boxes well above ground level.
 
 
The bundle of wires were attached to a fishtape ...
 
 
... then pulled upward ...
 
 
... and then finally through the opening.
 
 
Then it was time to get the wires attached where they needed to be attached. A test of the lighting system -- expected to run for about 12 hours -- may be run by the end of this week.
 
 
A view of the field from the southeast corner. Beautiful!