John D. Sulsberger

Memorial Stadium
Home (of the Blue Devils)
How You Can Help!
The Renovations
Photo Galleries / 2009
Photo Galleries / 2008
April 30, 2008
May 2, 2008
May 6, 2008
May 9, 2008
May 12, 2008
May 13, 2008
May 14, 2008
May 19, 2008
May 23, 2008
May 28, 2008
May 29, 2008
June 2, 2008
June 4, 2008
June 10, 2008
June 11, 2008
June 13, 2008
June 18, 2008
June 19, 2008
June 23, 2008
June 26, 2008
July 2, 2008
July 7, 2008
July 8, 2008
July 9, 2008 (Early)
July 9, 2008 (Late)
July 11, 2008
July 13, 2008
July 15, 2008
July 16, 2008
July 17, 2008
July 19, 2008
July 21, 2008 (Early)
July 21, 2008 (Late)
July 23, 2008
Aug. 4, 2008
Aug. 13, 2008
Aug. 15, 2008
Aug. 21, 2008
Who was John Sulsberger?
Building the Stadium-1964
Stadium Facts
The Latest News
Contact Us
Site Map
MAY 28, 2008
 A place for everything!
 
 
Surveyors were on site to lay out the field.
 
 
This precise measurement was to mark the end of what will be the pole vault runway
at the west end of the Stadium.
 
 
A spike with a white ribbon attached is driven into the rolled earth
to mark another key spot on the field.
 
 
Precise measuring will help assure that everything is going to be where it's supposed to be!
 
 
The surveyor's assistant uses two wooden stakes to help with accuracy.
 
 
This wider angle shows how far the project has come in just under one month of work. Up next -- installation of the concrete curb along the inside of the track that will border the new turf.